September 2023Pre-Development Begins
Demolition and site work begins.August 2023Financing Secured
Stonehill provides construction loan for Phase I.Q3-Q4 2021Planning & Execution
Identifying development partners along with ongoing in-depth architecture, planning and design work.Q2 2021Site Plan/Land Development
Final approvals expected for site plan and land development permitsMarch 2021
Land development permits submitted to City of CharlotteFebruary 2021
Site plan submitted to City of CharlotteJuly 2020Master Plan Approval
Preliminary approval of master plan by Mecklenburg CountyApril 2020Due Diligence Complete
BK Partners completes due diligence obligations.Dec. 26, 2019Due Diligence Begins
All documents from the City of Charlotte, Mecklenburg County and the Charlotte Housing Authority have been received and the due diligence period begins.2018-2019Contract Execution
A variety of activities occur in support of the Master Redevelopment Agreement. Once that checklist is completed, the developer will begin its formal due diligence.July 2018Master Redevelopment Agreement
Mecklenburg County and BK Partners, LLC entered into a Master Redevelopment Agreement and a License Agreement.2016-2018Negotiations
BK Partners and the County reviewed community input and went into negotiations to fine-tune the submitted proposal and create a Master Development Agreement. Negotiations included discussion about housing density and types, including affordable housing units, retail and commercial development, green space and park areas, and historic preservation. This led to contracts to purchase each of the sites and create the development as specified in the Master Development Agreement.Fall 2016Community Outreach
Over several months, BK Partners hosted 14 community meetings to hear more from Charlotte citizens and former Brooklyn residents about what they’d like to see for the project. Presentations from the meetings can be seen here.
MONDAY, AUGUST 15 MONDAY, AUGUST 29 MONDAY, SEPTEMBER 12THURSDAY, AUGUST 4
Kickoff Event
TUESDAY, AUGUST 16
History of Brooklyn and Cultural Programming
TUESDAY, AUGUST 30
MWSBE Participation and Outreach
TUESDAY, SEPTEMBER 13
Affordable Housing and Public Open Space
Slideshow Presentation
TUESDAY, SEPTEMBER 27 WEDNESDAY, OCTOBER 19 THURSDAY, OCTOBER 20MONDAY, SEPTEMBER 26
Economic Opportunity and Approach to Retail
Economic Opportunity and Approach to Retail
General Information Sessions
Click the times below to view videos from each session.
10:30 am Session
1:00 pm Session
3:00 pm Session
6:00 pm Session
Town Hall Meeting
June 2016
SelectionAfter the RFP responses were submitted and reviewed, interviews were held and additional feedback was provided by a steering committee and consultants. The Board of County Commissioners ultimately selected BK Partners LLC as their partner in the redevelopment. More information can be found here.Early 2016
RFPMecklenburg County received responses to an RFP and shortlisted three development teams including BK Partners consisting of Conformity Corp, The Peebles Corporation and Stantec. Mecklenburg County asked each team to come up with a proposed development plan and proforma based on preselected criteria and minimums that had been agreed upon by the Board of County Commissioners in 2015. More information can be found here.Fall 2015
RFQMecklenburg County released an RFQ soliciting respondents to qualify for participation in an RFP for a mixed-use development encompassing the 11.3-acre Brooklyn Village site and the five-acre Walton Plaza site in uptown Charlotte. The RFQ highlighted the need for a vibrant, active development that would also demonstrate sensitivity to the diversity of the Brooklyn community that was lost as a consequence of past redlining and urban renewal efforts that began in the 1930’s.